Sunday 8/25
We met down at the building around 9AM to continue grinding the back exterior mortar and to take down and rebuild scaffolding. We ended up getting a lot done over the weekend and hope to have the back fully ground out by the upcoming weekend. Thanks to Jeremy Bell and Glenn Hogenmiller for their help over the weekend.
Saturday 8/24
We really did a substantial amount of exterior grinding, finishing about half of the building. We ended up meeting with the two guys that will be doing some upcoming video work, Train Mayer and Matt Basler. They will be creating a video for us that will be posted on the website and the main video for our crowd-funding campaign. They should be around filming some of the September 7th Brewfest, so be prepared to say great things if you're approached for your thoughts on the beer, the upcoming brewpub, etc.
After building work, we had to prepare and finalize some financing documents, making for a nice little Saturday evening.
Friday 8/23
After we both worked at our actual jobs, we spent late afternoon Friday building scaffolding in preparation for a long weekend of brick grinding. The build went well. We had no injuries. No injuries during the building or dismantling of scaffolding usually means we had a good day.